Project Update - April 2021
The Options report has been completed and presented to Council for their review.
Project Update - March 2021
The Community Consultation Findings report has been completed while the Project Control Group have met and provided feedback on site locations and the proposed facility components. We are meeting to present at a Council briefing on the 6th of April.
Project Update - February 2021
The Beechworth Swimming Pool survey has now closed. We'd like to thank the 220 people who responded and the collection of the results are now underway. We are still taking written submissions for the project via email, the comments page accessible via the link above and our facebook page.
Project Update - January 2021
We are currently continuing with the community engagement stage of the project which includes the community survey, that closes on Wednesday the 27th of January. We are still taking written submissions for the project via email, the comments page and our facebook page so feel free to have your say by responding to one of the options provided. Currently, 193 surveys have been completed so far. Thank you to those who have completed one.
Project Update - December 2020
We have commenced the community engagement part of the project. You can provide your feedback on the Beechworth Swimming Pool by completing the survey or making a comment as outlined above.
Ways to get involved
- Fill in an online survey for residents. Closing Jan 27th, 2021
- Leave a brief comment about what swimming facilities are needed and where
- Visit the project Facebook page to make a comment
- Send us your thoughts via email to media@atleisure.com.au
- Comment on the plan when a draft is prepared
- To be kept updated, please subscribe via the 'leave your details' tab above.
More information
- Continue to visit this page for updates
- Contact the project manager Michael Graham @leisure Planners, ph. 0427 546 070
This project is expected to be completed in May 2021.